Vondelmolen Cooling System Modernization - PLC Upgrade, Energy Optimization & Remote Monitoring
REDI framework
R - Retrofit
E - Engineering
I - IIot
Services
- Retrofit & PLC Modernization
- Energy Optimization
- Operator Interface & Visualization
- IIoT & Smart Services (Remote Monitoring)
About Our Cases:
About the project
The client's cooling installation was controlled by a Siemens S5 PLC, an obsolete system that made maintenance difficult and expansion impossible. In addition, the installation had low energy efficiency, an obsolete operating interface, and a lack of remote monitoring, which limited the flexibility of the maintenance team. Reditech was hired to modernize the entire control system and prepare it for the future.
Challenge
- The main challenges of this project were:
- The Siemens S5 PLC was at the end of its life cycle and is no longer supported
- Lack of remote monitoring and control
- Low energy efficiency of the cooling groups
- An outdated operating interface without modern visualization
- Need for a reliable, future-proof platform
Our contribution
- PLC retrofit and modernization:
- Replacement of the Siemens S5 PLC with a modern Siemens S7-1200 controller
- Migration of all I/O signals, logic, and alarm systems to the new architecture
- More stable system thanks to modern hardware and error detection
Energy optimization:
- Implementation of energy-saving algorithms for the cooling groups
- Intelligent switching logic that controls the cooling installation more efficiently
- Improved temperature control for lower energy consumption
Operator interface and display:
- New Siemens Comfort Panel with modern and intuitive screens
- Clear visualization of temperatures, statuses, alarms, and energy consumption
- Better user experience and faster system management
IIoT and Intelligent Services (remote monitoring):
- Activation of Siemens Smart Services for secure remote access
- Operators and maintenance teams can now monitor and control the system remotely
- Faster interventions and less need for on-site presence
Results for the customer:
- Complete modernization of the cooling installation
- Better energy efficiency and lower operational costs
- Remote operation and monitoring, thanks to Smart Services
- User-friendly operator interface with improved visualization
- Future-proof platform with long-term support
- More efficient management and higher reliability of the installation
REDI pillars in this project:
R – Retrofit
Upgrade of an end-of-life S5 PLC to a modern S7-1200 solution
E – Engineering
Rewiring, PLC migration, energy optimization, and HMI integration
I – IIoT
Remote monitoring and control through Siemens Smart Services